K-III zone is located in the west part of the town, in Ljudevita Gaja street. It covers 3.4 ha. 9 construction plots and 2 plots for infrastructure facilities are foreseen in Zone, with average plot size of 2,425 sqm. Activities foreseen to be performed in Zone are: business, office, catering, tourist, service, utility-service and trading. Infrastructure is partially built (water supply, sewage system, gas supply), partially under construction (roads, phone) and partial in preparation stage (electricity supply).

Business conditions in Zone
The following business terms and conditions are currently valid in K-III zone :

INFORMATION ON ENTREPRENEURIAL ZONE:

Name of local self-government unit: THE TOWN OF VALPOVO
Name of entrepreneurial zone: ECONOMY/BUSINESS ZONE K -III
Name of location-place: VALPOVO
Zone address (street): LJUDEVITA GAJA STREET

ZONE DEVELOPMENT PROGRAMME:

Physical plans: DPU
Land surface area under physical plan (sqm.): approx. 3.4 ha (2.2 ha – economy/business, 0.85 ha green area protection, 0.34 ha area of infrastructure facilities)
Detailed designs: DETAILED DESIGN
Allocation of land performed: YES
Number of construction plots: 9 CONSTRUCTION PLOTS; 2 PLOTS FOR INFRASTRUCTURE FACILITIES
Average size of construction plot: THE LARGEST PLOT 7,972 sqm.; THE SMALLEST PLOT 998 sqm.; AVERAGE SIZE 2,425 sqm.
Plots available for sale: 1. K-3 1,103 m2; 2. K-4 1,046 sqm.; 3. K-6 1,665 sqm.; 4. K-7 1,419 sqm.5. K-8 2.,344 sqm.; 6.,K-9 2,279 m2
Price of 1sqm.of construction plot: kn 200,00 / sqm.
Utility contribution 1 cu.m.: kn 20,00 / cum.
Investments into zone made so far: kn 1,471,118.02
Total number of employers in zone: 3 ENTREPRENEURS
Number of entrepreneurs operating in zone:
Entrepreneurs operating in zone:
Number of employees:
Activities allowed to be performed in Zone: BUSINESS, OFFICE, CATERING, TOURIST, SERVICE, UTILITY-SERVICE, TRADING
Condition of utility infrastructure: IN PREPARATION: electricity supply; UNDER CONSTRUCTION : roads, phone; BUILT: water supply, sewage system, gas supply
Installed energetic supply capacities in zone: ELECTRICITY: 560 kW